Kathleen McCartney Hall
Announced in November 2023, Kathleen McCartney Hall will be a sustainable, inclusive, welcoming, and inspiring hub for career development and leadership training. With a “purpose-driven design,” the building will enable direct collaboration between the Lazarus and Wurtele Centers for the first time.
A Timeline for Success
Smithies will only need to wait a little over a year from the time of groundbreaking until the opening of this new, impactful space. Check out the timeline of major construction events.
Date(s) |
Details |
---|---|
February 12, 2024 |
The 8 College Lane parking lot permanently closed. |
March 12–22, 2024 |
Demolition of 8 College Lane will be underway. |
April 2024 |
Groundbreaking and foundation preparation will begin. Construction will continue through winter 2024 and spring 2025. |
Summer 2025 |
Kathleen McCartney Hall will open. |
Sustainability Front and Center
Following in the footsteps of the redesign of Neilson Library, this construction project is rooted in sustainability. Featuring responsibly sourced mass timber and a living roof, Kathleen McCartney Hall will soon be one of the most energy-efficient buildings on Smith’s campus.
Participant
in the Healthy Materials initiative
LEED Gold
certified
Geothermal
heating and cooling
Smith’s first
heavy timber construction
A Look Ahead
Take a sneak peek at the interior and exterior of Kathleen McCartney Hall.
Under Construction
Curious about how construction is coming along? Check out the progress with our two live webcams.